Traffic routes
How to cross the River Aare safely during construction
Because the Nydegg Bridge and Untertor Bridges are being renovated alternately, the other bridge serves partly as an alternate route for both private motorized transport and public transportation. A dedicated walkway will be set up on both bridges for pedestrians and cyclists. The walkway on Nydegg Bridge can be accessed via the arcades on Nydeggasse.
Detailed information on public transportation, pedestrian and bike traffic, and private motorized transport can be found under the individual project phases.
NydeggAdvance information
Nydegg Phase 1: February 2027 – December 2028
UntertorIn planning
Untertor Phase 1.1: From Spring 2029
UntertorIn planning
Untertor Phase 1.2: From approx. Autumn 2029
UntertorIn planning
Untertor Phase 2: From approx. Summer 2030
NydeggIn planning
Stage 1: Spring 2031 – End of 2033